Question: 1 / 400

What are interim controls designed to do?

Completely eliminate lead-based paint hazards

Temporarily reduce lead-based paint hazards

Interim controls are designed to temporarily reduce lead-based paint hazards rather than completely eliminate them. This approach is implemented when immediate abatement is not feasible or practical. Interim controls can include measures such as regular cleaning, maintenance of painted surfaces, and temporary barriers to prevent exposure. These actions are essential for managing risks in environments where lead-based paint is present, allowing for a safer living or working area while longer-term solutions are planned or enacted. Ultimately, interim controls serve as a bridge between initial hazard identification and the implementation of more permanent solutions.

Get further explanation with Examzify DeepDiveBeta

Provide a permanent solution for lead-based paint issues

Assess the effectiveness of lead hazard interventions

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy